| Date | Update |
|---|---|
| 15/10/2025 | Electrical work of the factory is completed and verified. |
| 10/10/2025 | Massive learnings from sampling efforts. We are inching ahead! |
| 25/09/2025 | Sampling has started. Excited! |
| 15/08/2025 | Furniture for offices completed. |
| 05/08/2025 | Machinery started arriving. |
| July | Rains disrupted work for days |
| 16/06/2025 | Offices, Storage Area, Lab, Reception Area finally done. |
| 10/06/2025 | Main electrical panel delivered and related work begins. |
| 09/06/2025 | Plumbing work finished. |
| 03/06/2025 | CCTV cable laying commences. Plumbing work progressing well. |
| 02/06/2025 | Plumbing work has begun. |
| 30/05/2025 | Electric cable work for lights and fans being carried out. |
| 25/05/2025 | Electric cable laying work for machinery done. |
| 12/05/2025 | Work on reception area has begun. |
| 10/05/2025 | Electrical work has begun. |
| 09/04/2025 | Factory layout is almost finalized. While you may have all things planned out in your head, the key is to have a person in the form of a pillar next to you who not only grounds you but also makes sure that all your plans come to fruition in a systematic manner. |
| 06/04/2025 | Electric Meter Installed. Our factory now has the power. |
| 28/03/2025 | Transformer upgraded. Finally! |
| 01/03/2025 | Work towards pollution control NOC has begun. |
| 28/02/2025 | Factory getting ready for production. Power related work commences. |
| 27/02/2025 | The research team is just amazing. Commendable work. Can't wait for the world to know about the amazing work we are doing! |
| 25/02/2025 | Discussions with machinery suppliers continue. |
| 24/02/2025 | Fruitful discussions with machinery suppliers. Highly optimistic about insights gained. |
| 29/01/2025 | Machinery Supplier Comparative Analysis Begins! |
| 27/01/2025 | GST Number Allocated! We are inching ahead! |
| 25/01/2025 | We are currently in the process of setting up a manufacturing unit. The factory premises has been finalized. Few tweaks at the premises and we will be ready to bring in the machinery. Working on clearances and regulatory approvals! Excited! |